Service/Server Information

PVFA has adopted the definition of “Significant IT Equipment” as defined in 29.01.03.M0.05 as what constitutes a server or service.

tip

See the other Service Information pages in this section for details on our Disaster Recovery Plans, Defined Roles and Responsibilities and any other relevant supporting documentation, this is also linked below in the Server and Services Lists.

Server List

ServerName:IPOSLocationPurpose
pvfa-services:10.174.6.133Windows/Server 2022AggieCloudSoftware, Print & Licensing Services
pvfa-sn0md0000:10.55.160.244Linux/Ubuntu 22.04Tegaue DatacenterGPU Cluster for Xin Li
pipeline:10.165.114.135Linux/AL2023AWSRender farm Pulse Webservice
pipeline:10.165.119.210Linux/AL2023AWSRender farm Repository
pipeline:10.165.62.12Linux/AL2023AWSClient Service CDK
pipeline:10.165.102.96Linux/AL2023AWSDCV Connection Gateway

Services List

ServiceLocationPurpose
Apple ManagementPublic CloudInfrastructure for Managing Apple (macOS, iOS, visionOS) devices
Linux ManagementPrivate CloudInfrastructure for Managing Linux devices
Windows ManagementPrivate CloudInfrastructure for Managing Windows devices
SassafrasPublic CloudITAM, Loaner Checkout
NetAppPrivate CloudStorage
Microsoft365Public CloudEmail, Azure, EntraID Services
Network & TelecommunicationsN/AVOIP
BeyondTrustPrivate CloudRemote Support
RenderFarmPrivate CloudRendering Farm
QualtricsPublic CloudSurvey Application
Universal PrintPublic CloudPrinting Services
TurbosquidPublic Cloud3d asset acquisition
Adobe Creative CloudPublic CloudCreative Suite Software

RACI

RACI Definitions

R = Responsible - the person who owns the project, task, or work. An example would be the executor of the task and not the project manager
A = Accountable - the person who will sign off on the work and judging its completion and how it meets quality standards. This could be the Project Sponsor or Project Manager whomever has final sign-off authority.
C = Consulted - the person who has the ability or knowledge needed to complete the work. These can be Stakeholders, Subject matter experts, or anyone else who can contribute consultatively to the task.
I = Informed - people who must be kept informed of the work but not necessarily consulted.

Management Groups

PVFA

This group is customer stakeholders within the College, comprised of PVFA Leadership, the Pipeline Group or Virtual Production Staff.

Technology Services PVFA (TSPVFA)

This group is the team that is housed in and supports PVFA but part of Technology Services (dotted line to PVFA)

Technology Services Server Administration Services (TSSAS)

This group is within Technology Services that the college partners with to operate services at scale.

Examples of these groups are the Server Administration group within Technology Services or the Academic Operations Linux team who we partner with to assist in managing servers or services.

3rd Party External Vendor (EXTVE)

This is the listing we use for External Vendors that we partner with to maintain some of our services.